ESL Multimedia Language Lab Project
Installation Update April 23, 2003
Look at what we're installing!
Randy Wu is managing the installation of the new computer
equipment. Installation slated for Spring Break April 7-11 has
begun, and more time is needed due to delay in delivery of equipment.
Accomplishments to date
- Macs were removed Thu-Fri Apr 3-4.
- Tables were removed Thu-Fri Apr 3-4.
- Network jacks were confirmed.
- New tables were received Mon Apr. 7.
- All tables were assembled and installed.
- Most of the new Pentium 4 PCs were received Mon Apr. 7 and
installed during that week. The remainder are due to arrive today,
along with monitors and cables.
- Installation of new computers commenced Mon Apr. 7.
- Several room configurations have been tried. Furniture layout
of April 23 is an improvement over original layout, providing
greater overall instructor and student accessibility, including
easy wheelchair access.
Tasks to come:
- Receipt and installation of remaining computer equipment
- Hardware & Software Inventory
- PC Computer Configurations & Imaging
- Software Application Tests and Configurations
- Final Documentation
- Training
- Desktop Support
Multimedia
Language Lab Project